A migration plan should include the schedule for parallel operation of the old and new systems. It defines how service and data move safely, including cutover timing, conversion, validation, responsibilities, fallback, user preparation, and any period during which both systems run.

Answer (b)

Why not others:
- system selection policy belongs to earlier planning or procurement

- deliverable quality criteria belong to quality and acceptance planning

- project members' work histories are staffing information

Key rule: Migration planning governs the controlled transition from existing operation to the new system.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.