ITPEC IP April 2021 Question 99
ITPEC IP April 2021 — Question 99 of 100
The correct order is issue the RFP, evaluate proposals, determine the contractor, and conclude the contract. The RFP communicates requirements and conditions; submitted proposals are compared with predefined criteria; the best supplier is selected; and the agreement is then negotiated and signed.
Answer (b)
Why not others:
- selection cannot properly precede proposal evaluation
- contracting must follow contractor determination
- issuing the RFP after selection or contracting defeats competitive procurement
Key rule: Procurement sequence is RFP → proposal evaluation → contractor decision → contract.