ITPEC IP April 2020 Question 52

Source exam: ITPEC IP April 2020Topic: Project Management

ITPEC IP April 2020 — Question 52 of 100

A project is a temporary endeavor undertaken to achieve a specific goal. It has a defined beginning and end and produces a unique result, service, or deliverable within constraints such as scope, time, cost, and quality.

Answer (a)

Why not others:
- team membership can change and different parties may own different processes

- a project should have completion criteria rather than beginning with no defined end

- work repeatedly performed as a routine is an operation, not a project

Key rule: Projects are temporary and unique; operations are ongoing and repetitive.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.