The function point method estimates system size from user-visible functions such as inputs, outputs, inquiries, interfaces, and logical files. Each function is counted and weighted by complexity, providing a size measure largely independent of programming language.

Answer (b)

Why not others:
- summing WBS activity estimates is bottom-up estimation

- estimating from lines of code is a code-size productivity method

- adjusting from a similar past system is analogy-based estimation

Key rule: Function points measure delivered functional size rather than source-code volume or task-by-task effort.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.