ITPEC IP October 2020 Question 67
When the planned production quantity of Product A and the total required quantity and the inventory quantity of Component B are as shown in the table below, what is the minimum order placement quantity I of Component B required in Week 2?
Explanation
30 — before each week's production the stock of Component B must cover that week's requirement plus a safety stock of 25% of it, and the order placed at the end of Week 2 fills Week 3's gap.
- •Week 1: 100 − 80 = 20 left, which matches the table and equals the safety stock 80 × 0.25 = 20
- •End of Week 1: Week 2 needs 80 + 20 = 100; order 100 − 20 = 80
- •Week 2: 100 − 80 = 20 left after production
- •End of Week 2: Week 3 needs 40 + 40 × 0.25 = 40 + 10 = 50; order I = 50 − 20 = 30
Answer (a)
Why not others:
- •(b) 40 — orders Week 3's requirement in full, ignoring both the 20 already in stock and the safety stock of 10
- •(c) 60 — would put 80 in stock at the start of Week 3, 30 more than the 50 needed, so it is not the minimum
- •(d) 80 — is the order placed at the end of Week 1 for Week 2's production of 40 products, not the order for Week 3
Key rule: Order quantity = next period's requirement + required safety stock − stock left over; compute it for the period the order will be used in.