The project should agree with the customer in advance on how change requests will be prioritized and controlled. When many requests arise, an established priority and decision procedure allows the highest-value changes to be selected while schedule, cost, scope, and quality effects are assessed.
Answer (d)
Why not others:
- refusing every post-design change is inflexible and may reject essential business needs
- skipping tests protects neither quality nor delivery reliability
- automatically cancelling unspecified functions is not a controlled, customer-approved response
Key rule: Anticipated change should be handled through agreed priorities and formal change control, not arbitrary refusal, scope removal, or reduced testing.
AI-generated — may contain errors
The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.
This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.