ITPEC IP October 2020 Question 100
Which of the following items is determined when computerization plan is created on the basis of a company’s information system strategy?
Explanation
Development schedule — the computerisation plan turns the information system strategy into concrete system projects, each with its scope, schedule and cost.
From the top down:
- •Management strategy sets the management objectives
- •Information system strategy decides how IT will support those objectives across the company
- •Computerisation plan decides, for each system, its scope and priority, the development schedule, the rough cost and expected effects, and the development organisation
- •Requirements definition and design then fix what the system does and how: screens, forms, hardware and software configuration
Answer (a)
Why not others:
- •(b) — management objectives come first, from the management strategy; they are the input to the information system strategy and the plan, not something the plan decides
- •(c) — the output screen layout is decided in design (external design), after requirements definition
- •(d) — the hardware configuration is decided in system design (system architecture design), once the requirements are known
Key rule: Each stage fixes what the next needs: strategy the objectives, the computerisation plan the scope, schedule and cost, requirements what the system does, and design how it looks and runs.