ITPEC IP October 2019 Question 45
ITPEC IP October 2019 — Question 45 of 100
Risk treatment selects how each evaluated risk will be handled and plans the specific controls to implement. Possible treatments include avoiding the activity, reducing likelihood or impact, transferring consequences, or accepting the remaining risk.
Answer (d)
Why not others:
- finding risks is risk identification
- comparing risk levels with acceptance criteria is risk evaluation or assessment
- calculating risk from probability and impact is risk analysis
Key rule: Identification finds risk, analysis estimates it, assessment evaluates priority, and treatment chooses and implements the response.