Restoration to Tuesday closing requires Sunday's full backup plus both Monday's and Tuesday's incremental backups. The full backup establishes the base. Monday's incremental contains changes since Sunday, and Tuesday's contains only changes since Monday, so both increments must be applied in order.

Answer (a)

Why not others:
- omitting the full backup leaves no complete base image

- applying Tuesday without Monday omits changes captured only in Monday's increment

- neither incremental file alone contains all data needed for the target state

Key rule: Restore an incremental-backup chain from the latest full backup, then apply every subsequent incremental backup chronologically.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.