Blank B is the confirmation of order sent by Company X to the customer. The sequence is: Company X sends an estimate; the customer sends a purchase order at A; Company X confirms the order at B; after fulfillment the customer sends an acceptance certificate at C; and Company X sends the invoice at D.
Answer (c)
Why not others:
- the acceptance certificate flows from the customer to Company X after delivery, so it belongs at C
- the invoice flows from Company X to the customer near the end, so it belongs at D
- the purchase order flows from the customer to Company X after the estimate, so it belongs at A
Key rule: A typical sales-document flow is estimate → purchase order → order confirmation → acceptance → invoice.
AI-generated — may contain errors
The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.
This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.