ITPEC IP April 2019 Question 67

A company wants to perform an acceptance inspection on an outsourced part with a non-defective probability of 0.9 and defective probability of 0.1. The table below shows four (4) proposed acceptance inspections with their respective cost per non-defective and defective part. Which of the following is the plan with the lowest expected cost?

PlanCost per non-defective partCost per defective part
A01,500
B401,000
C80500
D120200

Explanation

Plan C — its expected cost per part, 122, is the lowest of the four.

Expected cost = 0.9 × cost per non-defective part + 0.1 × cost per defective part:

  • •A: 0.9 × 0 + 0.1 × 1500 = 0 + 150 = 150
  • •B: 0.9 × 40 + 0.1 × 1000 = 36 + 100 = 136
  • •C: 0.9 × 80 + 0.1 × 500 = 72 + 50 = 122
  • •D: 0.9 × 120 + 0.1 × 200 = 108 + 20 = 128

Answer (c)

Why not others:

  • •(a) A — 150: it spends nothing on good parts, but 1,500 on each defective part is the largest weighted term of any plan
  • •(b) B — 136, a middle ground that is still 14 above plan C
  • •(d) D — 128: it has the lowest cost per defective part, but paying 120 on each of the 90% good parts outweighs that saving

Key rule: Weight each outcome's cost by its probability before comparing; judging by one column alone (cheapest per good part gives A, cheapest per defective part gives D) ignores how often each case happens.