ITPEC IP April 2019 Question 54
ITPEC IP April 2019 — Question 54 of 100
Finishing earlier by parallelizing work to capture a cost-saving opportunity is treatment of a positive risk. A positive risk is an uncertain event that could benefit project objectives, and the project can act to exploit or enhance that opportunity.
Answer (b)
Why not others:
- vaccination mitigates the negative risk of staff absence
- securing replacement staff mitigates the negative risk of withdrawal
- insurance transfers financial exposure from the negative risk of delay
Key rule: Threat responses reduce harmful uncertainty; opportunity responses increase the probability or benefit of favorable uncertainty.