Analyzing the previous delay and incorporating preventive measures reduces the probability or impact of another delay, so it is risk mitigation. The project still uses Company A, but changes the plan to make the identified risk less likely or less damaging.
Answer (a)
Why not others:
- canceling the subcontract removes the source of risk and is avoidance
- contractual compensation shifts financial consequences and is transfer
- budgeting for a possible delay acknowledges the risk and is acceptance
Key rule: Mitigation acts to reduce probability or impact; avoidance removes the threat, transfer shifts consequences, and acceptance prepares to tolerate it.
AI-generated — may contain errors
The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.
This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.