ITPEC IP April 2018 Question 48

Source exam: ITPEC IP April 2018Topic: System Development Technology

ITPEC IP April 2018 — Question 48 of 100

A migration plan should include the schedule and human resources required to switch from the current system to the new one. Cutover activities must be assigned, timed, coordinated, rehearsed, and supported with rollback and verification arrangements to reduce operational disruption.

Answer (d)

Why not others:
- functional requirements belong to requirements definition for the new system

- screen and form usage belongs to operational manuals or user training

- routine backup procedures belong to ongoing operations planning rather than the one-time migration plan

Key rule: Migration planning covers data conversion, cutover method, schedule, roles, resources, validation, fallback, and transition risks.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.