ITPEC FE Morning April 2023 Question 70

Source exam: ITPEC FE Morning April 2023Topic: Corporate & Legal

ITPEC FE Morning April 2023 — Question 70 of 80

Production Capacity / Bottleneck Analysis — find which process cannot meet the required monthly output.

For each process, calculate max units per month:

capacity = (number_of_machines × hours_per_machine) / manufacturing_time_per_unit

  • A: (3 × 150) / 0.4 = 1125 units
  • B: (2 × 160) / 0.3 = 1066 units
  • C: (4 × 170) / 0.7 = 971 units
  • D: (7 × 180) / 1.2 = 1050 units

Only process C produces fewer than the required 1,000 units → it is lacking in capability.

Why not others:
- (a) A — capacity is 1,125, exceeds 1,000

- (b) B — capacity is ~1,066, exceeds 1,000

- (d) D — capacity is 1,050, exceeds 1,000

Key rule: Total capacity = (machines × hours/machine) ÷ time per unit. The bottleneck is the process whose capacity falls below the production target.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.