ITPEC FE Morning October 2022 Question 69

Source exam: ITPEC FE Morning October 2022Topic: System Strategy

ITPEC FE Morning October 2022 — Question 69 of 80

Project Management — calculating total development cost across multiple methods using person-month costs.

For each method, total cost = purchase cost + outsourcing cost + Σ(persons × months × rate per process).

Rates: creation = $6,000/person-month; modification = $10,000/person-month; evaluation = $10,000/person-month.

  • (a) 200,000 + (4×3×10,000) + (1×2×10,000) = $340,000 ✓ cheapest
  • (b) 350,000 flat = $350,000
  • (c) (10×3×10,000) + (3×2×10,000) = $360,000
  • (d) (10×6×6,000) + (2×2×10,000) = $400,000

Why not others:
- (b) Outsourcing flat fee ($350k) exceeds option (a)

- (c) 10 people in modification × 3 months drives cost to $360k

- (d) 10 people in creation × 6 months = $360k alone, plus evaluation

Key rule: Always calculate person-month cost as persons × months × rate for each process separately, then sum all cost components.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.