PDCA Cycle in Security Risk Management — identify which phase an activity belongs to.
The PDCA cycle applied to security risk management:
- •Plan — establish security policy, develop the risk management plan
- •Do — implement the risk management plan
- •Check — monitor security risks as planned
- •Act — maintain and improve the plan by learning from incidents
Why not others:
- (a) — belongs to Plan (establishing policy and developing the plan)
- (b) — belongs to Do (implementing the plan)
- (d) — belongs to Check (monitoring as planned)
Key rule: Act = continuous improvement based on lessons learned. Look for keywords like "improve," "correct," "learn from."
AI-generated — may contain errors
The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.
This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.