ITPEC FE Morning October 2022 Question 38

Topic: Security

When security risk management processes incorporate the approach of the PDCA (Plan, Do, Check, Act) cycle, which of the following is a process that belongs to Act?

Explanation

Maintain and improve the plan by learning from incidents — Act takes what Check revealed and turns it into corrective action and improvement.

Security risk management mapped onto PDCA:

  • •Plan: set the security policy and develop the risk management plan
  • •Do: implement the plan
  • •Check: monitor the risks and evaluate the results as planned
  • •Act: correct and improve the plan based on those results and on incidents

Answer (c)

Why not others:

  • •(a) — establishing the policy and developing the plan is Plan
  • •(b) — carrying out the plan is Do
  • •(d) — monitoring the risks as the plan prescribes is Check

Key rule: Act closes the loop: it feeds the findings of Check back into the next Plan. Look for "improve", "correct" or "learn from" to spot it.