ITPEC FE Morning April 2021 Question 71

Source exam: ITPEC FE Morning April 2021Topic: Management Strategy

ITPEC FE Morning April 2021 — Question 71 of 80

To find how many units of component C are needed to produce 10 units of product A, we "explode" the BOM:

BOM structure (per 1 unit of A):
- A requires: B(2) and C(1)

- Each B requires: D(1), E(1), and C(1)

Step 1 — Gross requirement of C per 1 unit of A:
- C directly under A: 1

- C through B: 2 × 1 = 2 (since A needs 2 B's, each B needs 1 C)

- Total per A: 1 + 2 = 3

Step 2 — Gross requirement for 10 units of A:
- 3 × 10 = 30

Step 3 — Subtract inventory on hand:
- 30 - 5 = 25

Why not others:
- (a) 15 — only counts C through B (2 × 1 × 10 = 20) minus 5, ignoring the direct C under A

- (b) 20 — counts only the C nested inside B (2 × 1 × 10 = 20) without subtracting inventory, or miscounts paths

- (d) 30 — correct gross requirement but forgets to subtract the 5 units already in inventory

Key rule: In MRP BOM explosion, a component can appear at multiple levels — sum ALL paths from the finished product to that component, then subtract existing inventory to get the net order quantity.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.