ITPEC FE Morning April 2021 Question 58

When the PDCA methodology is applied to a service management system, which of the following corresponds to Act?

Explanation

Taking actions to continually improve the service management system and services — Act closes the PDCA cycle by acting on what Check found.

ISO/IEC 20000 applies Plan-Do-Check-Act to the service management system (SMS):

  • •Plan: establish, document and agree the SMS
  • •Do: implement and operate the SMS for the design, transition, delivery and improvement of services
  • •Check: monitor, measure and review the SMS and services against policies, objectives and requirements, and report the results
  • •Act: take actions to continually improve the performance of the SMS and services

Answer (d)

Why not others:

  • •(a) — establishing, documenting and agreeing the system is Plan
  • •(b) — implementing and operating the system is Do
  • •(c) — monitoring, measuring, reviewing and reporting is Check

Key rule: In any PDCA-based management standard, Check measures and reports, and Act turns those results into improvements that feed the next Plan.

Service Management · AI-written, may contain errors