ITPEC FE Morning April 2021 Question 56

Source exam: ITPEC FE Morning April 2021Topic: IT Service Management

ITPEC FE Morning April 2021 — Question 56 of 80

A migration test verifies the procedure for switching from the existing system to the new system and identifies reliability and efficiency problems that the switch may cause.

  • Migration test — validates the cutover process itself (data transfer, rollback plans, downtime impact)
  • Function test — confirms the new system has all required features
  • Performance test — checks throughput using real data copies
  • Integration test — verifies interface compatibility between systems

Why not others:
- (a) — describes a function test (does the system do what it should?)

- (b) — describes a performance test (can it handle real workloads?)

- (c) — describes an integration test (do interfaces between systems work?)

Key rule: Migration test = testing the switch procedure, not the system's features or performance.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.