ITPEC FE Morning October 2021 Question 72

Source exam: ITPEC FE Morning October 2021Topic: Management Strategy

ITPEC FE Morning October 2021 — Question 72 of 80

MRP (Material Requirements Planning) follows three core steps:
1. Gross requirement — using the production plan and BOM (Bill of Materials), calculate total component quantities needed.

2. Net requirement — subtract available inventory to determine actual order quantities.

3. Order timing — schedule orders by working backward from the needed date using manufacturing and procurement lead times.

Why not others:
- (a) CAD — Computer Aided Design is for product design/drafting, not material planning

- (b) CRP — Capacity Requirements Planning deals with production capacity (machines, labor), not materials

- (c) JIT — Just In Time is an inventory philosophy focused on minimizing stock, not a step-by-step BOM-based calculation system

Key rule: MRP answers three questions — what to order, how much to order, and when to order — all derived from the BOM and production schedule.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.