ITPEC FE Morning October 2019 Question 73

Source exam: ITPEC FE Morning October 2019Topic: Corporate & Legal

ITPEC FE Morning October 2019 — Question 73 of 80

MRP (Material Requirements Planning) — calculate component needs from production plans and existing inventory.

MRP follows three core steps:

  1. Gross requirement — using the production schedule and BOM (Bill of Materials), calculate how many components are needed
  2. Net requirement — subtract available inventory to find the actual order quantity
  3. Order timing — schedule orders backward from the need date, accounting for manufacturing or procurement lead time

Why not others:
- (a) CAD — Computer-Aided Design; used for engineering drawings, not material planning

- (b) CRP — Capacity Requirements Planning; plans production capacity (machines, labor), not materials

- (c) JIT — Just-In-Time; a lean manufacturing philosophy that minimizes inventory, but does not describe this specific three-step calculation process

Key rule: MRP answers three questions — what to order, how much to order, and when to order.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.