Among the descriptions below, which of the following lists all and only the problems that can occur because the business requirements definition is ambiguous?
Explanation
C, D — an ambiguous business requirements definition shows up later, as rework from specification changes and as acceptance tests that cannot be designed.
Business requirements definition comes after planning: it fixes what the business needs from the system, and everything after it is built and checked against it.
- •A: the computerization concept and its approval belong to the planning process, which is finished before requirements are defined, so an ambiguous requirements definition cannot cause it
- •B: a coding error is a mistake in implementing a design; the program misbehaves even when the requirements are clear
- •C: requirements left vague get settled during development, so specifications change and work done already is redone
- •D: acceptance testing checks that the system meets the agreed requirements; vague requirements give no clear criteria to test against
Answer (d)
Why not others:
- •(a) A, B — both problems arise elsewhere: A in planning, before requirements exist, and B in coding
- •(b) B, C — includes the coding error B and leaves out D
- •(c) B, D — includes the coding error B and leaves out the rework C
Key rule: Requirements are the baseline for design and for acceptance; when they are vague, the cost appears as rework and untestable acceptance criteria.