IPA IP 2023 Question 54
A question IPA Japan published in 令和5年度 ITパスポート試験 公開問題 問54, translated into English. ITPEC is based on the same exams.
Same question on ITPEC: Oct 2024 Q51
Among the descriptions A through D below concerning project management in system development, which of the following lists all and only the failures in scope management?
Explanation
C, D — both fail to define the work the project must deliver, which is what scope management does.
- •A Underestimated labor costs overrun the budget: a cost management failure.
- •B Too little time set for the work misses the planned period: a schedule management failure.
- •C Starting without deciding which functions to build leaves the product scope undefined: a scope failure.
- •D Omitting required activities from the plan leaves the project scope (the WBS) incomplete: a scope failure.
Answer (d)
Why not others:
- •(a) A, B — both are cost and schedule failures, and neither scope failure is listed
- •(b) B, C — includes B, a schedule estimate, and omits D
- •(c) B, D — includes B, a schedule estimate, and omits C
Key rule: Classify a failure by its cause, not its symptom: C also overran the period, but the root error was undefined scope, not a bad time estimate.
Project Management · AI-written, may contain errors