IPA IP 2023 Question 54

A question IPA Japan published in 令和5年度 ITパスポート試験 公開問題 問54, translated into English. ITPEC is based on the same exams.

Same question on ITPEC: Oct 2024 Q51

Among the descriptions A through D below concerning project management in system development, which of the following lists all and only the failures in scope management?

A:The labor costs incurred in development were underestimated, so the budget was exceeded.B:The time required for development work was set short, so development could not be completed within the planned period.C:A project was started without first deciding the function to be created, so the development period is exceeded.D:Several activities that should be implemented in a project were omitted from the plan, so the system could not be completed.

Explanation

C, D — both fail to define the work the project must deliver, which is what scope management does.

  • •A Underestimated labor costs overrun the budget: a cost management failure.
  • •B Too little time set for the work misses the planned period: a schedule management failure.
  • •C Starting without deciding which functions to build leaves the product scope undefined: a scope failure.
  • •D Omitting required activities from the plan leaves the project scope (the WBS) incomplete: a scope failure.

Answer (d)

Why not others:

  • •(a) A, B — both are cost and schedule failures, and neither scope failure is listed
  • •(b) B, C — includes B, a schedule estimate, and omits D
  • •(c) B, D — includes B, a schedule estimate, and omits C

Key rule: Classify a failure by its cause, not its symptom: C also overran the period, but the root error was undefined scope, not a bad time estimate.

Project Management · AI-written, may contain errors

This question comes from the past questions IPA Japan publishes, translated into English by ITPEC Practice. ITPEC Practice is an independent study tool and is not affiliated with IPA or ITPEC. See the original paper (PDF) or Report an issue.