IPA IP 2020 Question 69

Topic: Security

A question IPA Japan published in 令和2年度 10月 ITパスポート試験 公開問題 問69, translated into English. ITPEC is based on the same exams.

Among the following implementation items in the establishment, implementation, maintenance and continual improvement of an ISMS, which of the following is performed first?

Explanation

Understanding the needs and expectations of interested parties — the ISMS starts from its context, before any risk work.

ISO/IEC 27001 (JIS Q 27001 in Japan) orders the work by its clauses:

  1. Context of the organization (clause 4): the internal and external issues, the needs and expectations of interested parties such as customers, regulators and staff, and from these the scope of the ISMS
  2. Planning (clause 6): information security risk assessment, then risk treatment
  3. Operation (clause 8): carrying out the assessments and the treatment plan
  4. Performance evaluation (clause 9): monitoring, internal audit, management review

Risks can only be assessed against requirements and a scope that are already known, so understanding interested parties comes first.

Answer (d)

Why not others:

  • •(a) — risk assessment is planning work that needs the scope and requirements fixed first
  • •(b) — risk treatment follows risk assessment, since it chooses controls for the risks found
  • •(c) — an internal audit checks an ISMS that is already running, so it comes late in the cycle

Key rule: In ISO/IEC 27001 the order is context and interested parties, then risk assessment, then risk treatment, then operation, then audit and review.

Security · AI-written, may contain errors

This question comes from the past questions IPA Japan publishes, translated into English by ITPEC Practice. ITPEC Practice is an independent study tool and is not affiliated with IPA or ITPEC. See the original paper (PDF) or Report an issue.